Planet Fitness Canada

PTU Migration Dashboard

Data as of ·

Completion Velocity

Dated installs only

At Risk, need help to push

Open items blocking an install date
ItemClubs ImpactedResponsibleStatusDetails
Morgan StanleyInstall date passed
  • White Rock (91826)
Morgan StanleyNot migratedInstall was confirmed for Fri, Oct 23, and hardware has been on site since Aug 14. ABC Tech Support confirmed Oct 28 that the club has not migrated, with no movement for 43 days. The franchise says the club has used Ingenicos since presale, but Logically and the club confirm it is still on Verifone and Clover. Need from Morgan Stanley: devices installed by Oct 30.

Install Schedule

Hide clubsShow clubs
ClubResponsibleInstall DateDetails

Status by Franchise Group

Click a row to see clubs
GroupTotalDoneLeftStatusInstall OwnerRisk
Prepared by Code Blue · Sources: ABC progress reports and tracking (Misty Wells), Taymax install updates (Sarah Giroux), UPS tracking, Code Blue tracker